CDMC Projects
Project
Nurse Call Upgrade, Yeovil District Hospital, Somerset.
Client
Yeovil District Hospital NHS Trust, Higher Kingston, Yeovil, BA21 4AT.
Consulting Designers
Eric Marsh Design, "Sparshatts", Broad Oak, Botley, Southampton, SO30 2EU.
Contract Administrator
Facilities Department, Yeovil District Hospital NHS Foundation Trust, Higher Kingston, Yeovil, BA21 4AT.
Principal Contractor
Bowshers Electrical Services Ltd, 19 Buckland Road, Yeovil, BA21 5HA.
Description
This project is to upgrade the Nurse call system to all wards 6A, 6B, 7A, 7B & 9B.
These works were carried out whilst the hospital was open. Consequently works had to be programmed so as not to disturb the normal running of the hospital or to cause disturbance to patients.
Asbestos was found to some ceilings, mainly bathrooms, and this was removed by a licensed asbestos removal company as part of these works.
Yeovil District Hospital has 322 beds and provides in/outpatient services in gen & respiratory medicine, cardiology, urology, paediatrics, care of the elderly, rheumatology, gastroenterology, diabetes, dermatology, surgery, trauma & orthopaedic surgery, gynaecology, obstetrics, A&E, ENT, oral/maxillary-facial surgery, orthodontics, radiology, histopathology and haematology.
Situation
Ongoing